From initial survey and sizing to delivery and positioning

FW Power has delivered and positioned a 275 kVA prime-rated open type diesel generator for a self storage facility in London, reaching the next milestone in a project to provide standby power for life safety equipment.
The delivery and positioning took place on , following our initial site survey and generator sizing work. Final connection, testing and commissioning will follow. The project continues a relationship spanning the past two years, during which FW Power has supplied generators for the same customer’s self storage facilities across the UK.
Standby power planned around life safety equipment
For this London facility, the brief centred on backup power for life safety equipment. FW Power’s involvement began with understanding the requirement and sizing the generator for its intended duty. That early work set the direction for the equipment supply and the move into the building.
From the survey to the plant room
Survey and generator sizing before delivery
Our initial survey and sizing work established the generator requirement for this site. The selected unit has a prime rating of 275 kVA and is intended for standby service. The rating describes the generator’s capacity under a defined duty; standby describes its role in this project, providing backup when the normal supply is unavailable.
Sizing a standby generator involves the loads it must support, their starting demands and the way they are brought online. A site survey also brings the practical installation requirements into the discussion, including access, positioning and the space available for the equipment.
An open type generator for an indoor plant room
The supplied Blackwell generator uses a Baudouin diesel engine and an open type arrangement, with the engine, alternator and radiator mounted on a common base. The photographs show the generator and its FW Power-branded control cabinet inside the plant room.
Open type installations require the room and its services to be designed around the generator, including cooling air, exhaust discharge, noise control and maintenance access. The room forms part of the overall installation design.
Delivery and positioning on a working site
The delivery photographs tell the story of the physical move: arrival on the haulage vehicle, handling with a telehandler, and movement through the plant room doorway on machinery skates. Protective wrapping remained around the generator during the move, with the equipment subsequently positioned inside the room.





This is where the earlier planning becomes visible. The route through the building, the doorway and the final position all matter. Bringing a generator into an indoor plant room takes coordination between the delivery team and the people working on site, with attention to each stage of the move.
Two years of repeat business across the UK
FW Power has continued supplying this customer’s UK self storage facilities over the past two years. We value that ongoing relationship and the opportunity to support another of their sites. Repeat projects allow us to build on our understanding of the customer’s requirements while assessing each location on its own merits.
Thank you TEAM FW Power
Once again, a big thank you to TEAM FW Power for the hard work behind this project. From the initial discussions and survey through sizing, preparation, delivery coordination and positioning, every contribution has helped move the job forward. The photographs capture the work on site, but they also represent the effort that took place before the vehicle arrived.
We are proud of the care and commitment our team brings to these projects, and grateful to our customer for continuing to place their trust in FW Power.
The next stage
With delivery and positioning complete, the project now moves towards the remaining installation work, final connection, testing and commissioning. Those stages will establish the system’s operation before it enters service as standby power for the facility’s designated life safety equipment.
Frequently asked questions
What size standby generator does a self storage facility need?
Generator size depends on the equipment being backed up, its running load, starting demand and operating sequence. This London project uses a 275 kVA prime-rated unit following survey and sizing work. Other facilities may need a different capacity, even where the buildings appear similar.
Why is a prime rated generator being used for standby power?
A prime rating describes an operating duty and capacity. A standby application describes the generator’s use as backup to the normal supply. This unit is rated at 275 kVA prime and is intended for standby service; its permitted loading and operation remain subject to the manufacturer’s specification.
Can an open type diesel generator be installed indoors?
Yes, a fixed open type generator can be installed in a properly engineered plant room with suitable ventilation, exhaust discharge, fuel arrangements and service access. Indoor suitability depends on the complete installation design. Placing a generator in a room does not make it ready to operate.
Can a generator provide backup power for life safety equipment?
Yes, where it is specified and integrated for the building’s designated life safety loads. The equipment to be supplied and the required system response must be established for that project. At this London site, life safety backup is the intended application and commissioning is still to follow.
Does delivery and positioning mean the generator is commissioned?
No. Delivery and positioning put the equipment in place. Commissioning follows completion of the installation and checks the agreed system operation. For this project, delivery and positioning took place on 20 November 2026; final connection, testing and commissioning remain to follow.
Can FW Power support generator projects at several UK storage sites?
Yes. FW Power has supplied generators for this customer’s self storage facilities across the UK over the past two years. Each new project starts with the requirements of the individual site, supported by the working relationship developed through previous supplies.
What should I provide when requesting a generator installation quote?
Share the site location, equipment to be backed up, any available load schedule, proposed generator position and target programme. Access photographs and drawings are useful too. FW Power can then discuss the survey, generator selection and installation scope with you.